GATE 2013 Electronics and Communication Engineering (EC) Slot 4 - Offline Question Paper with Answer Key pdf is available for download. The exam was conducted by IIT Bombay on February 10 in the Afternoon Session. In terms of difficulty level, GATE Electronics and Communication Engineering (EC) Slot 4 - Offline was of Moderate to Difficult level. The question paper comprised a total of 65 questions from General Aptitude and Electronics and Communication Engineering (EC) Slot 4 - Offline topics.
GATE 2013 Electronics and Communication Engineering (EC) Offline Question Paper with Answer Key PDF- Slot 4- Afternoon Session
GATE 2013 Electronics and Communication Engineering (EC) Question Paper PDF
GATE 2013 Electronics and Communication Engineering (EC) Answer Key PDF
The actual demand for castings in a factory is \(500\) units and \(635\) units for the months of January 2026 and February 2026, respectively. The forecasted demand for January 2026 is \(250\) units and the smoothing constant is \(0.7\). Using the exponential smoothing method, the forecast of the demand for castings in March 2026 is ________ units (in integer).
A metal has an FCC crystal structure with a density of \(2.71\) g/cm\(^3\) and atomic weight of \(26.98\) g/mol. Avogadro's number is \(6.023 \times 10^{23}\). The atomic radius of the metal is ________ nm (rounded off to 2 decimal places).
The inventory holding cost of an item is Rs. \(0.50\) per unit per month and the ordering cost per order is Rs. \(550\). A stockist needs to supply \(10000\) units of the item per year to the customers. Assume demand is fixed and the shortage cost is infinite. Using the classical economic order quantity (EOQ) model, the optimal lot size is ________ units per order (rounded off to the nearest integer).
The activities of a PERT network and their corresponding activity time estimates (in weeks), namely optimistic (\(t_o\)), most likely (\(t_m\)), and pessimistic (\(t_p\)), are given in the table below.
Activity
\(t_o\)
\(t_m\)
\(t_p\)
1-2
2
4
12
1-3
2
4
6
1-4
3
4
11
2-5
3
6
9
3-4
2
5
14
3-5
3
3
3
4-5
3
6
15
5-6
2
5
8
The expected project length is ________ weeks (in integer).
Convective heat transfer coefficients for Fluid 1 and Fluid 2 in a heat exchanger, as shown in the figure below, are 50 W/(m2K) and 80 W/(m2K), respectively. The inner tube is made of a material which has a thermal conductivity 386 W/(m K) for the given range of temperatures in the heat exchanger. The length of the heat exchanging surface, the inside radius of the inner tube, and thickness of the inner tube are 1 m, 10 mm, and 1 mm, respectively. Considering no heat exchange between the outer tube and the surrounding, the heat transfer rate for the heat exchanger is ________ W (rounded off to 1 decimal place).
A welded square plate of 1 m \(\times\) 1 m is subjected to biaxial stress of magnitude 6.5 MPa and 25 MPa, as shown in the figure below. The ratio of the normal stress acting in the perpendicular direction of the weld to the shear stress of the weld is ________ (rounded off to 2 decimal places).
Comments